What is the NZ Transport Agency's total expenditure to date on Takitimu North Link Stage 2, if any, broken down by financial year and by project phase?

Answered Question 31815 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What is the NZ Transport Agency's total expenditure to date on Takitimu North Link Stage 2, if any, broken down by financial year and by project phase?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

2024/25 Pre Implementation $4 million Implementation “Early Works” $0.888 million Property $5.9 million 2025/26 (as at 31 May 2026) Pre Implementation $19.3 million Implementation “Early Works” $4.9 million Property 39.4 million