Answered
Question 31800 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
What is the NZ Transport Agency's total expenditure to date on the SH2 Hawke's Bay Expressway, if any, broken down by financial year and by project phase?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
2024/25 Investment Case $6 million Pre Implementation $12.7 million Implementation $0.382 million Property $0.124 million 2025/26 (as at 31 May 2026) Pre Implementation $19.7 million Implementation $49 million Property $0.49 million