Answered
Question 31794 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
How much, if any, does the NZ Transport Agency expect to spend on public consultation and community engagement in relation to the Petone to Grenada Link Road over the remainder of the 2024-27 National Land Transport Programme period?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
The budget allows $15,000 for communications and engagement within the remainder of the 2024/27 NLTP. However, actual expenditure will depend on project needs throughout the remainder of the NLTP and may be lower than the amounts budgeted.