What is the NZ Transport Agency's total expenditure to date on Otaki to north of Levin, if any, broken down by financial year and by project phase?

Answered Question 31785 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What is the NZ Transport Agency's total expenditure to date on Otaki to north of Levin, if any, broken down by financial year and by project phase?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

2024/25 Pre Implementation $1.2 million Implementation $99.8 million Property $67 million 2025/26 (as at 31 May 2026) Pre Implementation $0.454 million Implementation $236.5 million Property $14.6 million