Question
-
What is the NZ Transport Agency's total expenditure to date on the SH1 Belfast to Pegasus Motorway and Woodend Bypass, if any, broken down by financial year and by project phase?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
2024/25 Investment case $1.2 million Pre Implementation $8.6 million Property $7.4 million 2025/26 (as at 31 May 2026) Pre Implementation $19 million Implementation “Early Works” $5.7 million Property $26.6 million