When is main construction of the Northwest Busway (Te Ara Hauāuru) Stage 1A, listed in the July 2026 Major Transport Projects Pipeline, expected to begin?

Answered Question 31454 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • When is main construction of the Northwest Busway (Te Ara Hauāuru) Stage 1A, listed in the July 2026 Major Transport Projects Pipeline, expected to begin?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Detailed design of the first stage of Brigham Creek Rārawaru station is underway. Enabling works are expected to start in early 2027, with construction completed by early 2029.