Skip to main content

What NZTA co-funding, if any, is committed to the Auckland Level Crossings Removal at Takaanini?

Answered Question 31445 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What NZTA co-funding, if any, is committed to the Auckland Level Crossings Removal at Takaanini?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Work to remove level crossings at Takaanini and Glen Innes is being progressed as one priority package. The total cost to deliver the Takaanini and Glen Innes level crossing replacements is expected to be $815 million, funded jointly by the Government and Auckland Council. In early 2025, NZTA confirmed $200 million in funding for the first three years of this work.