Skip to main content

When is the Airport to Botany Busway Stage 2, listed as a council-led project in the July 2026 Major Transport Projects Pipeline, expected to be completed?

Answered Question 31444 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • When is the Airport to Botany Busway Stage 2, listed as a council-led project in the July 2026 Major Transport Projects Pipeline, expected to be completed?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Subject to funding, construction is expected to begin in 2028 after pre-implementation is complete and next steps are confirmed. The completion date is still to be confirmed.