Skip to main content

What NZTA co-funding, if any, is committed to the Airport to Botany Busway Stage 2?

Answered Question 31443 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What NZTA co-funding, if any, is committed to the Airport to Botany Busway Stage 2?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

NZTA has committed $1.7 million from the National Land Transport Fund to the Airport to Botany Stage 2 pre-implementation phase, representing a 51 percent funding assistance rate of the $3.4 million total cost, including administration. Approximately $52 million of implementation funding is identified in the Regional Land Transport Plan, with the level of NZTA co-funding to be confirmed following completion of the pre-implementation phase and confirmation of construction costs.