What works are included in the SH29 Tauriko (wider scope) project in Phase Two of the July 2026 Major Transport Projects Pipeline, and how do they differ from the SH29 Tauriko (Ōmanawa Bridge) works in Phase One?

Answered Question 31426 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What works are included in the SH29 Tauriko (wider scope) project in Phase Two of the July 2026 Major Transport Projects Pipeline, and how do they differ from the SH29 Tauriko (Ōmanawa Bridge) works in Phase One?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The Phase Two SH29 Tauriko (wider scope) project includes route protection, consenting, strategic property acquisition, design activities, and technical investigations for the wider Tauriko West corridor improvements. The Phase One SH29 Tauriko (Ōmanawa Bridge) project is a separate construction project to replace the existing bridge, including associated road realignment and intersection improvements. It is being progressed ahead of the wider Tauriko project because the existing bridge is nearing the end of its service life.