Why is SH6 Hope Bypass Stage 2 placed in Phase Three of the July 2026 Major Transport Projects Pipeline while SH6 Hope Bypass Stage 1 is placed in Phase Two?

Answered Question 31395 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Why is SH6 Hope Bypass Stage 2 placed in Phase Three of the July 2026 Major Transport Projects Pipeline while SH6 Hope Bypass Stage 1 is placed in Phase Two?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

As outlined in my press release of 9 July 2026, intersection improvements (stage 1) are being prioritised at Lower Queen Street. This will provide safety improvements for locals, while ensuring that further work on the project can continue when funding becomes available.