Answered
Question 31390 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
When are route protection or main construction of the Airport to Botany Busway Stages 3 and 4, listed as a council-led project in Phase Three of the July 2026 Major Transport Projects Pipeline, expected to occur, if a date has been set?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
Route protection is already complete for stages 3 and 4. The 2021 Single Stage Business Case recommended staged delivery: the western section (Airport–Manukau via Puhinui) in the next decade, followed by the eastern section (Manukau–Botany) between 2036 and 2047, subject to Auckland RLTP and 30-Year Plan priorities and funding.