Answered
Question 31386 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
Why is the Cross Valley Link shown at feasibility/investment-case stage in the July 2026 Major Transport Projects Pipeline when its investment case was described alongside Petone to Grenada in the Government's 20 October 2025 announcement?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
The Cross Valley Link project is being progressed by Hutt City Council. It has an important network relationship with the Petone to Grenada (P2G) project but does not form part of the P2G scope.