Have construction contracts been signed for the port-side infrastructure at Picton and Wellington required to berth the two new Cook Strait ferries, and if not, when are they expected to be signed?

Answered Question 30348 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Have construction contracts been signed for the port-side infrastructure at Picton and Wellington required to berth the two new Cook Strait ferries, and if not, when are they expected to be signed?

Answered by

Rt Hon Winston Peters

List MP · NZ First · Minister for Rail

Answer

Yes, for early contractor involvement and various demolition and design tasks. Main works contracts will be entered later this year, as planned.