Is the new Fire and Emergency New Zealand fault management system still on schedule for Phase One to launch on 30 October 2026?

Answered Question 30266 (2026)
Question published
Reply lodged

Asked by

Mike Davidson

List MP · Green Party

Question

  • Is the new Fire and Emergency New Zealand fault management system still on schedule for Phase One to launch on 30 October 2026?

Answered by

Hon Brooke van Velden

Member for Tāmaki · ACT Party · Minister of Internal Affairs

Answer

I am advised by Fire and Emergency New Zealand that implementation of the new fault logging system, ServiceNow, is phased. This allows training, adoption, triage arrangements, and service-provider processes to be embedded. Phase one (the technical build) was completed by 30 June 2026. The system has been tested, including testing with operational users, and deployment commences in July 2026 with District-by-District onboarding and training. Implementation and rollout are due to be completed by December 2026.