- Question published
- Reply lodged
Asked by
Camilla Belich
List MP · Labour Party
Question
-
Which agencies, departments, Crown entities, companies, or other organisations for which the Minister is responsible, if any, have been required to identify or deliver baseline savings or staffing reductions since 27 November 2023, and how much, if anything, has each delivered, broken down by organisation and year, as at 5 June 2026?
Answered by
Hon Mark Mitchell
Member for Whangaparāoa · National Party · Minister for Ethnic Communities
Answer
I am advised by the Ministry for Ethnic Communities (the Ministry) that the Ministry was required to deliver baseline savings of 6.5% from the 2024/25 financial year and out years, and a further 2% for the 2026/27 financial year and out years. This equates to savings of $1.255 million and $.277 million respectively.