How many, if any, of the 14 Wellington region state housing projects that were “not proceeding” in Kāinga Ora’s June 2025 Pipeline Review Register had a business case with an expected delivery date in FY26 and what was the address of any such projects?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Housing
Answer
Kāinga Ora – Homes and Communities advises me that four of the 14 Wellington region state housing projects had an indicative business case with an estimated original delivery year of FY26. The list of the projects by address is in the attachment provided by Kāinga Ora.