Answered
Question 17241 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Ayesha Verrall
List MP · Labour Party
Question
-
What was the original approved budget for Taranaki Base Hospital Redevelopment - Project Maunga - Stage 2 at the time funding was first established, if any?
Answered by
Hon Simeon Brown
Member for Pakuranga · National Party · Minister of Health
Answer
I am advised the original budget approved for Taranaki Base Hospital Redevelopment - Project Maunga - Stage 2 was $336,960,000.