Answered
Question 17238 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Ayesha Verrall
List MP · Labour Party
Question
-
Has the approved budget for Taranaki Base Hospital Redevelopment - Project Maunga - Stage 2 increased since funding was first approved, if so, by how much has the budget increased in total, on what dates were budget increases approved, and what were the reasons for each budget increase, if any?
Answered by
Hon Simeon Brown
Member for Pakuranga · National Party · Minister of Health
Answer
I am advised that the approved budget for Taranaki Base Hospital Redevelopment - Project Maunga - Stage 2 has increased since funding was first approved. I refer the Member to the following press release: https://www.beehive.govt.nz/release/59-million-boost-ensure-completion-taranaki-base-hospital-redevelopment