On what date, if at all, was he first notified that Kāinga Ora agreed to changes that saw the Hutt City Council stormwater project approved through the Infrastructure Acceleration Fund reduced from two projects to a single solution and what action, if any, did he take as a result? and 1 other question

Answered 12324, 12325 (2026)
Questions published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Questions

  • 12324

    On what date, if at all, was he first notified that Kāinga Ora agreed to changes that saw the Hutt City Council stormwater project approved through the Infrastructure Acceleration Fund reduced from two projects to a single solution and what action, if any, did he take as a result?

  • 12325

    On what date did Kāinga Ora first agree to changes that saw the Hutt City Council stormwater project approved through the Infrastructure Acceleration Fund reduced from two projects to a single solution and how was any such agreement communicated to the Hutt City Council?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Housing

Answer

I was first notified of Kainga Ora’s preferred option through their briefing I signed on 17 March 2025. Only the responsible ministers can approve any variations to the IAF agreement, and the Minister of Finance agreed with me to the variation on 27 March 2025. Kainga Ora notified Hutt City Council after the variation was approved. This is also my answer to WPQ 12325 (2026).